KEEP MELDRETH ROAD LEVEL CROSSING SAFE

KEEP MELDRETH ROAD LEVEL CROSSING SAFEKEEP MELDRETH ROAD LEVEL CROSSING SAFEKEEP MELDRETH ROAD LEVEL CROSSING SAFE

KEEP MELDRETH ROAD LEVEL CROSSING SAFE

KEEP MELDRETH ROAD LEVEL CROSSING SAFEKEEP MELDRETH ROAD LEVEL CROSSING SAFEKEEP MELDRETH ROAD LEVEL CROSSING SAFE

NETWORK RAIL IGNORE PLANNING INQUIRY VERDICT!

NETWORK RAIL IGNORE PLANNING INQUIRY VERDICT! NETWORK RAIL IGNORE PLANNING INQUIRY VERDICT! NETWORK RAIL IGNORE PLANNING INQUIRY VERDICT!

DOWNTIMES WILL INCREASE FROM CURRENT 50 SECONDS TO UP TO 7 MINUTES Make your opinion known BY NOVEMBER 10th LATEST!


NETWORK RAIL IGNORE PLANNING INQUIRY VERDICT!

NETWORK RAIL IGNORE PLANNING INQUIRY VERDICT! NETWORK RAIL IGNORE PLANNING INQUIRY VERDICT! NETWORK RAIL IGNORE PLANNING INQUIRY VERDICT!

DOWNTIMES WILL INCREASE FROM CURRENT 50 SECONDS TO UP TO 7 MINUTES Make your opinion known BY NOVEMBER 10th LATEST!


PROPOSED CHANGES TO MELDRETH ROAD LEVEL CROSSING

What's Happening?

So why did the Planning Inspector REJECT the change? And how can Network Rail proceed?

So why did the Planning Inspector REJECT the change? And how can Network Rail proceed?

Network Rail plan to change the Meldreth Road barrier to one like Shepreth Station's at Christmas/New Year 2025 - in just a few weeks. 


Because of the strength of local objections to another level crossing change like the one that has caused such problems at Shepreth, a Planning Inquiry was held in April 2023. 


At it the Planning Inspector agreed with the objections and ruled the change should not proceed.


Because while there would be a reduction in the potential risk of an accident involving a road user and rail that it would create bigger NEW risks elsewhere:

'I conclude that there is not a compelling case in the public interest.. for the purpose of the level crossing upgrade elements at this location... and should not be approved in the foreseeable future'



In addition at the Inquiry Network Rail's submission was shown to be flawed by the fact that:

- they had done only onee 4 hour traffic survey, during the pandemic

- their model was wrong - 'at least some of NR's own staff did not properly understand the modelling work' (the Planning Inspector)

- as an example, the letter local homes received from NR in November 2022 stated an impact of 2 seconds.... at the Inquiry the author of the modelling that informed that admitted 'the barrier downtime will increase by an average of 107 seconds, with a maximum increase of 428 seconds in am peak'. 428 seconds is 7 MINUTES!

- many of the 'incidents' reported at the barrier were removed/redacted as it was realized they related to other barriers...


He also criticized the overall value for money of the crossings - 'NRs calculations indicate that the cost of the upgrades would be more than five times the benefits in terms of the forecast reduction in injuries and fatalities. Moreover NR confirmed that the Cost Benefit Ration calculation does not include any allowance for the the costs which would arise as a result of the level crossing upgrades in terms of increased delays to road users'. The Meldreth Road change is expected to cost around £2 million. 


At the same time NR say they have no money to fund a crossing at Shepreth Station, which would have far more utility and likely reduce risks as much or more.


(By the way I actually don't commute across it myself, and live 500 m from it. But I foresee this creating significant problems for many. Clearly most of those who will badly affected know nothing about it.


'Yes but how would you feel if an accident happens and its because the barrier hasn't been changed?'. Well I'd feel really bad! But its about balancing risks. NRs data, which they admit overegged the safety impact, is for a reduction in fatalities from one per 54 years to one per 922 years. Is it more likely that a big increase in downtime will create more risk either from a death due to delay in emergency vehicles or from a speeding car hitting a pedestrian? The Inspector's answer was 'yes'. Its trade offs - if the road was closed up there would be a zero risk....)








So why did the Planning Inspector REJECT the change? And how can Network Rail proceed?

So why did the Planning Inspector REJECT the change? And how can Network Rail proceed?

So why did the Planning Inspector REJECT the change? And how can Network Rail proceed?

Simply put, because while it would slightly reduce road/rail risk it would increase other risks by far more:


1 - Increased risk from cars speeding (to beat new barriers which will be down for up to 5 minutes vs current 50 seconds)


2 - Massive increased risk to Meldreth residents, as all emergency service either wait extra 3-4 minutes at barrier OR divert down A10 and back up Meldreth High Street, at least 7 minutes. Network Rail don't even CONSIDER that apparently until AFTER permission granted!!!


3 - Inconvenience and traffic queues from much longer down times - current 50 seconds will increase to Shepreth's or WORSE. Someone crossing 4 times a day can look forward to at least ten minutes a day wasted...


Don't take my word for it:


You can find the Inspector's Report here:

 Network Rail (Cambridge re-signalling) order inspector's report 


And the letter from the Department of Transport here:

 Network Rail (Cambridge re-signalling) order decision It is true that a double barrier makes it impossible for either a car/pedestrian/cyclist to cross when the barrier is down. 


ALSO


1. The local Rail User Group has no evidence of any incidents or near misses at the crossing throughout the 14 years of its existence.


2. There have been no accidents at the crossing that a double barrier would have helped prevent. In fact to see Network Rail's data required a Freedom of Information request and only came on 1st September, despite the September 23rd objections deadline. In the past 25 years according to that Network Rail data there has been one recorded incident where a double barrier could potentially have improved safety (and even this was NOT classified as a 'near miss). Almost half of the 'incidents' weren't even related to the crossing but to others in the area and misrecorded!


3. It will reduce train usage. Anyone crossing to catch Cambridge bound trains from Shepreth have to allow for ~5 minutes of downtime potentially at both Meldreth Road crossing and then at Shepreth station (which has no footbridge). For some at least it won't feel worth the hassle and they'll now drive instead.


4. The new longer downtime crossing has its own risks. Double barriers stop cars crossing with a barrier down, but also stop a car being able to get off the track if trapped by barriers. During the week of August 15th 2022 at Shepreth after a very long down time frustrated drivers were crossing nose to tail, and the barriers came down again with a car between them. Luckily there was room for it to get off the track just about before a fast train came through. 


5. Only issues for those very near the crossing, but the new crossing will likely require floodlighting like the Shepreth station one. And since the downtime would increase NOT from 2 minutes to 3 and a half, but from 50 seconds to almost four minutes, their traffic modelling is wrong and those living close to the crossing will have constant traffic queues outside their homes.


The bottom line is that Network Rail are going to create a problem on the road where none exists, in order to 'fix' what they have themselves decided is a risk on the railway, despite no evidence of any problem.


To see just how bad the impact will be see what happened when exactly the same change was made at Shepreth Station as reported in the Royston Crow - barriers which are down for exactly the same trains. As the Network Rail representative then said, '3 to 5 minutes is the expected time for the barriers to be down'. That compares to 50 seconds now and the downtimes of 7 minutes+ that frequently happen at Shepreth.

 Shepreth level crossing: Frustrations put to Network Rail at Meldreth RUG meeting | Royston Crow (royston-crow.co.uk)


SO WHY ARE NETWORK RAIL PRESSING AHEAD?

A legitimate issue is that sooner or later the current barriers WILL need replacing. And clearly when works need doing we do have to accept temporary road closures - fair enough. But NR had originally suggested an upgrade which would MAINTAIN current downtimes - which would be 'the best of both worlds'. Now they say that is not possible, because...

 THEY have decided not to work on upgraded half barriers and only replace them

 THEY have decided there is risk at Meldreth Road (based on  evidence admitted to be incorrect at the Inquiry)

THEY have decided only double barriers like at Shepreth Station can replace them. 

And when planning has been rejected, THEY have decided to do it ANYWAY - because THEY are ONLY responsible for and measured on rail safety, not on any transferred risks some of which are only considered and planned for AFTER permission and construction. 

What can you do about it?

So why did the Planning Inspector REJECT the change? And how can Network Rail proceed?

What can you do about it?

The 'ORR' or Office of Rail and Road is due to give final approval by mid November.



IF YOU WANT YOUR VOICE HEARD YOU NEED TO:


Email the ORR on

contact.pct@orr.gov.uk


Email our MP

pippa.heylings.mp@parliament.uk

and her assistant james.wilkin@parliament.uk


Email our local Councillors (Peter McDonald and Bridget Smith):

Peter.McDonald@cambridgeshire.gov.uk

Bridget.Smith@councillor.online


Email Network Rail's Communications Manager for the Scheme - 

stephen.deaville@network.rail.co.uk



SCROLL DOWN FOR AN EXAMPLE LETTER/EMAIL YOU CAN USE OR ADAPT!



Example Letter/Email

Attached is a draft letter/email you can adapt or use as is to make your voice heard!

EXAMPLE LETTER (txt)Download
EXAMPLE LETTER (pdf)Download

Copyright © 2025 Meldreth Road Level Crossing - All Rights Reserved.

Powered by

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

DeclineAccept